A new progress update from the Government of the Virgin Islands on the long-delayed rehabilitation of the Ralph T O’Neal Administration Complex (RTOAC) has reignited scrutiny over one of the territory’s most controversial ongoing public infrastructure projects, and the mounting cost to the public purse.
According to the “Ralph T O’Neal Administration Complex Priority Project Progress Report” released by the government this week, interior rehabilitations are now moving forward toward the tender phase after final designs were completed in January.
The RTOAC, once a central headquarters for the operations of the Government of the Virgin Islands, has been unusable since suffering extensive damage during the 2017 Hurricanes. Nearing a decade later, the building remains closed.
Beyond inconvenience, the scattering of government operations throughout Road Town and beyond has come at a monetary cost to the public. In the absence of a central administration building, the government has had to rent private office spaces over the years. According to Minister for Communications and Works Honorable Kye Rymer in September 2025, “Taxpayers are currently incurring over $2 million each year in rents and related costs for ministries and departments housed in temporary facilities”. He added that these expenses will be avoided once operations return to the RTOAC.
Members of the public have been very vocal in criticizing the project’s timeline, and the related rent expenses incurred in the absence of a completed RTOAC. Arguments have also been made that the drawn-out timeline has created a situation where the already completed components of the project have begun to deteriorate before interior rehabilitation works can commence. Most recently, the building was treated for mould. There have also been reports of pests, including rats, inhabiting the facility.
Above all, calls have been made for the government to move quickly to complete the project.
The release identified completion of a Bill of Quantities as the next step in the project but gave no specific timeline for the completion of this step.
The Government’s last update on the expected completion of the project, delivered by Rymer, placed substantial completion in the fourth quarter of 2026 and full commissioning in the second quarter of 2027. It is important to note however, that this timeline was based on several factors, including the anticipated completion of the internal designs by October 2025, and the commencement of tendering in November 2025, which at the time delayed the project timeline by approximately 2 months. The completion of the designs in January 2026 was 3 months behind that already delayed schedule.